Marc Jones

Marc Jones

Director
Client
Dublin City Council
Architect
Grafton Architects
Conservation Architect
Blackwood Associates Architects
Landscape Designer
Cunnane Stratton Reynolds
Public Lighting
Kevin Cleary & Associates
Archeology
CRDS Ltd
Market

About the Royal Canal Phase 2 scheme

The Royal Canal Phase 2 scheme provides a high-quality cycle track, footway and linear park from Guild Street to North Strand Road and includes a multi-span viaduct over the railway. The scheme forms part of the Royal Canal Greenway which, when complete, will provide a first-class, multi-purpose, off-road walking and cycling link from Cloondara on the River Shannon in County Longford through to the River Liffey in Dublin City.

Royal Canal Phase 2 Viaduct scheme

The Royal Canal Phase 2 Viaduct is a critical piece of infrastructure within the Royal Canal Greenway scheme and will enable pedestrians and cyclists to travel from the North Strand Road through to the Seville Place junction unobstructed.

At the western end of the scheme, the North Strand Road side, the viaduct Iinks to the recently installed ROD designed Newcomen Footbridge, which spans over the Docklands Railway Line and the Royal Canal and serves as a pedestrian bridge running parallel to the existing Newcomen Road Bridge.

The viaduct will take pedestrians and cyclists over the Newcomen railway line coming out of Connolly Station and onto a newly constructed, landscaped, winding approach ramp. From here, pedestrians and cyclists will be taken under the main northern line railway bridges and along approximately 500m of newly refurbished bank of the Royal Canal to the Seville Place junction.

Solution

The viaduct is 112m in length and consists of seven spans. It is a steel composite structure,
with a concrete deck made composite with a steel box girder beneath. The deck
is monolithic with six tapering steel piers and supported on bearings at a concrete pier at the
support closest to the Newcomen Cycle Bridge and a concrete abutment at its eastern end. 

Due to its length, the viaduct could not be constructed in a single length, and the team had
to consider, therefore, various constraints when determining the optimum construction
sequence. The primary constraint was the requirement to construct the bridge over the live
railway. 

To de-risk the construction process, the decision was made to install the steel girder over
the railway line first. This meant that as the subsequent steel girders were installed, any
issues with regard to construction tolerance could be addressed without impacting the
railway line. 

The deck for spans either side of the railway corridor are formed with in-situ concrete while
the deck over rail is formed with precast concrete, thus reducing work over the live railway.

Challenges

Delivering a simple, sculptural and elegant bridge solution that worked in harmony with the
surrounding streetscape and infrastructure provided a key challenge for the design team of
ROD, Grafton Architects, Kevin Blackwood and Kevin Cleary Lighting. 

The design team needed to find a way of taking pedestrians and cyclists from the relatively
low-lying Newcomen Bridge, over the Newcomen railway line and back down again
underneath the main northern line railway bridges supporting the railway coming from
Connolly Station. 

The solution had to comply with: 

  • maximum gradients allowable for bridges of this nature 
  • vertical clearance requirements for a structure located overhead a railway line
  • permissible clearance requirements for pedestrians and cyclists passing underneath a structure

Due to the bridge’s close proximity to Connolly Station, the team also had to ensure that the
bridge solution did not impact either the train divers’ ability to see the signals located
around the site or the cables and ducts in the vicinity. 

As part of the initial design process, various bridge types were considered. Ultimately the
design team concluded that a bridge with steel piers and composite deck was the most
advantageous solution. The use of steel piers and a steel box girder forming part of the deck
allowed for the majority of the bridge to be fabricated off-site in a controlled environment
which assisted greatly with on-site assembly. 

The adoption of steel as the primary bridge component facilitated a slender sinuous bridge
solution. The bridge piers were designed to taper vertically to highlight to the observer how
they “hold” the girder in place. The main steel girder that forms part of the deck taperes in
section to maximise apparent slenderness in elevation.  Provision of main steel girder with monolithic piers negates the use of bearings at intermediate support thus reducing
maintenance requirement. 

A 5.2m wide concrete slab made composite with the steel box girder completes the
construction of the bridge. This provides a 4m deck surface for pedestrians/cyclists and
0.6m concrete upstands on either side of the walking surface to accommodate services. As
the concrete deck cantilevers over the steel box girder underneath, it creates a drop
shadow, highlighting the slenderness of the structure.

Innovations

When adopting steel components in a bridge structure, providing a satisfactory corrosion protection system is vital. The external face of the steel piers and steel box girder have, therefore, been applied with a robust corrosion protection system in accordance with the relevant requirements.

Knowing that the slender nature of the bridge piers and girder would make it impossible to inspect the internal steel components once it was constructed, the design team took the decision to hermetically seal both the piers and main girder.  This proved challenging as the bridge was assembled from pier and girder segments that arrived on-site and were installed at different times.  To overcome this challenge, the designers installed full height diaphragms at the ends of each bridge component, sealing the majority of the bridge components.  This enabled the seal for each component to be tested in the fabrication shop prior to arrival on-site.  As a result, the only sections of the bridge that needed to be tested on-site were the small sections of the bridge joints located between the full height diaphragms at the end of each bridge component.

To minimise maintenance liability to Dublin City Council, the bridge is made continuous over its length with full connections at each pier reducing the requirement for bearings and joints.

Services provided:

  • Engineering consultancy
  • Bridge design
  • Site supervision
  • Contract administration
  • Project Supervisor Design Process (PSDP)
Bridge

Interested in our bridge work? Check out our recent projects